Hantam mayor hands over 25 new homes as Calvinia housing project reaches 75% completion

-Advertisement-spot_img

Must read

By Levy Masiteng

Hantam Municipality mayor Koos Alexander on Monday handed over 25 newly completed houses to beneficiaries at the Calvinia 200 Housing Project in the Northern Cape, bringing the project to 151 completed homes, or 75% of its target.

The remaining 49 houses are at various stages of construction and are expected to be completed and handed over by the end of September 2026.

The Northern Cape Department of Cooperative Governance, Human Settlements and Traditional Affairs (CoGHSTA) said the handover, conducted alongside MEC Bentley Vass, forms part of the provincial government’s R1 billion housing programme aimed at reducing the housing backlog across the province.

The Calvinia development is one of several projects under the province’s flagship housing programme launched two years ago to accelerate the delivery of subsidised housing.

According to the department, beneficiaries were selected from municipal housing demand databases, with priority given to vulnerable groups, including older

You’ve reached your free article limit

Subscribe to enjoy unlimited access to trusted journalism. Start your free trial today.

Start your FREE trial now

Need help? molokom@insideeducation.co.za

-Advertisement-spot_img

More articles

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Inside Education Quarterly Print Edition

spot_img

CATHSSETA

spot_img

QCTO

spot_img

AVBOB STEP 12

spot_img

Inside Metros G20 COJ Edition

spot_img

JOZI MY JOZI

spot_img

Inside Education Quarterly Print Edition

spot_img

Latest article